| 1 |
Sectional Replacement Of 10” Amukpe Export Pipeline |
NIGERIAN PETROLEUM DEVELOPMENT COMPANY (NPDC) |
Construction and Repairs of Pipelines, NDT, Hydrotest, Cathodic Protection |
Amukpe |
Completed |
| 2 |
Flowline Relocation |
Heirs Holding Oil and Gas (HHOG |
Mobilization To Site,
Excavation and Repositioning
Of Flowlines, Pipe Stringing
Along R.O.W, Pipe Welding, TieIn’s, Radiographic Examination
Of Welded Joints, Field Joint
Coating (Sleeve Application),
Lowering Of Flowlines,
Flushing And Hydro-Test,
Backfilling Of Trench, Valves
Replacement, Site
ReInstatement And
Demobilization |
Agbada OML 17 |
On-going |
| 3 |
Modification Works in SPDC
Producing Assets-Land |
Shell Petroleum
Development Company
(SPDC |
Workshop pre-fabrication, NDT,
Hydrotest, grot blasting and
painting, Instantiation,
precommissioning and
commissioning |
SPDC Land Assets |
On-going (5 + 2years) |
| 4 |
CONSTRUCTION OF WELL-05
WH-PLATFORM AND
Flowline Construction -
OML-40 |
NPDC/ELCREST
EXPLORATION AND
PRODUCTION |
Fabrication & Installation of
Well head platform,
Construction of Flowline,
NDT, Hydrotest, Cathodic
Protection |
Gbetiokun, Delta State |
Completed |
| 5 |
GBETIOKUN 10"
CONSTRUCTION OF CRUDE
LOADING PIPELINE AND
TOPSIDE PIPING PROJECT -
EPF TO STORAGE VESSEL |
NPDC/ELCREST
EXPLORATION AND
PRODUCTION
|
Construction of Flowlines,
NDT, Hydrotest, Cathodic
Protection |
Gbetiokun, Delta State |
Completed |
| 6 |
CONSTRUCTION OF WELL-09
WH-PLATFORM AND
FLOWLINE CONSTRUCTION
AND TESTING - OML-40 |
NPDC/ELCREST
EXPLORATION AND
PRODUCTION |
Fabrication & Installation of
Well head platform,
Construction of Flowline, NDT,
Hydrotest, Cathodic Protection |
Opuama, Delta state |
Completed |
| 7 |
Work-over Campaign and Associated Services. |
Total E & P Nigeria limited |
|
Omoku Rivers State, Nigeria |
Completed |
| 8 |
Mbede 3 well |
NAOC/AOS Orwell |
|
Ebocha Onelga Rivers State, Nigeria |
Completed |
| 9 |
IGBOLO 1 well |
Chorus Energy |
|
Kwale, Delta State |
Completed |
| 10 |
A WORKOVER OPERATION |
|
|
GELE-GELE-5 BENIN CITY |
Ongoing |
| 11 |
OML-100 FLARE REDUCTION PROJECT |
TOTAL ENERGIES |
Flare reduction Piping and
E&I works for Ime, Afia and
Edikan fields comprising
OML100 |
KIme, Afia & Edikan fields, Delta state |
Completed |